In short: Section 11 of the Real Estate (Regulation and Development) Act, 2016 sets out the duties of the promoter (builder). The promoter must keep the project page on the RERA website updated, including quarterly progress; is responsible for all obligations under the agreement for sale until conveyance; must obtain the completion and occupancy certificates; must enable the formation of an association of allottees; must execute a registered conveyance deed in favour of each allottee; and must pay outgoings (such as land cost, ground rent and taxes) until physical possession is handed over. Section 12 makes the promoter liable for false advertisements.
हिंदी में: धारा 11 रेरा: बिल्डर के कर्तव्य — रेरा वेबसाइट पर जानकारी, अधिभोग प्रमाणपत्र प्राप्त करना, आवंटियों का संघ बनवाना, पंजीकृत हस्तांतरण विलेख निष्पादित करना।
Section 11 RERA at a glance
| Provision | What it says (summary) |
|---|---|
| 11(1)-(2) | Create and update the project page on the RERA website, including quarterly progress. |
| 11(3) | Disclose stage-wise schedule of completion, including provisions for civic infrastructure. |
| 11(4)(a) | Responsible for all obligations under the Act and the agreement for sale until conveyance to allottees and the association. |
| 11(4)(b) | Obtain the completion certificate or occupancy certificate and make it available. |
| 11(4)(e) | Enable formation of an association of allottees within three months of a majority booking. |
| 11(4)(f) | Execute a registered conveyance deed in favour of the allottee (see Section 17). |
| 11(4)(g) | Pay outgoings until possession is handed over. |
| 11(5) | Booking can be cancelled by the promoter only in terms of the agreement for sale. |
| Section 12 | Compensation or refund for false statements in an advertisement or prospectus. |
The table summarises the provisions in plain English. For the exact words and the State rules (UP RERA, Delhi RERA), see the Act on India Code.
Pending registry and OC
Section 11(4)(b) and (f) are the provisions usually invoked when a builder has given possession without an occupancy certificate or has not executed the registry. In Noida and Greater Noida, this often involves the builder’s dues to the development authority; see flat registry not done in Noida or Greater Noida and Section 17.
Cancellation by the builder
Under Section 11(5), the promoter can cancel an allotment only in terms of the agreement for sale. An allottee aggrieved by an unfair cancellation can approach the Authority. Forfeiture clauses that are one-sided may not be enforced in full.
Maintenance until handover
The promoter must provide and maintain essential services at reasonable charges until the association of allottees takes over (Section 11(4)(d)). Disputes about maintenance charges and handover are common; see RWA and AOA disputes.
Duties listed in Section 11
- Display the registration number and the RERA website address on every advertisement and prospectus (Section 11(2)).
- Make available the sanctioned plans, layout, specifications and the stage-wise completion schedule (Section 11(3)).
- Remain responsible for all obligations under the Act and the agreement until the conveyance of all apartments and common areas (Section 11(4)(a)).
- Obtain the completion certificate or occupancy certificate and make it available to allottees (Section 11(4)(b)).
- Enable formation of the association of allottees within three months of a majority of allottees having booked (Section 11(4)(e)).
- Execute the registered conveyance deed (Section 11(4)(f)).
- Pay all outgoings, including land cost, ground rent, municipal taxes, water and electricity charges, mortgage loan and interest, until physical possession is transferred (Section 11(4)(g)).
- Not cancel an allotment except in terms of the agreement for sale (Section 11(5)).
The 70 per cent escrow rule
Section 4(2)(l)(D) requires the promoter to deposit 70 per cent of the amounts realised from allottees into a separate bank account, to be used only for the cost of construction and land of that project, with withdrawals certified by an engineer, an architect and a chartered accountant. The account must be audited every year. This rule is a frequent ground of complaint where projects stall despite large collections, and the Authority can investigate the use of funds.
Step by step: holding the promoter to its duties
- Read the promoter’s declaration and quarterly updates on the RERA portal.
- Compare the advertised amenities with what is delivered, and keep the brochure.
- Write to the promoter citing the specific duty breached under Section 11.
- File a complaint under Section 31 for directions, and seek investigation if diversion of funds is suspected.
- Act collectively through the association for common-area issues.
Common mistakes
- Accepting cancellation of an allotment outside the agreement’s terms.
- Paying land dues or taxes the promoter was bound to pay before possession.
- Not using the quarterly updates as evidence of delay.
An example
A promoter in Ghaziabad hands over possession but keeps collecting maintenance from residents while refusing to transfer the society’s funds and records to the newly formed association. The association writes to the promoter citing Section 11(4)(d) and (e), and then files a complaint before UP RERA asking for directions to hand over the maintenance account, the common area documents and the audited statements. The Authority can direct the promoter to comply within a fixed time and can impose a penalty for non-compliance. Individual residents can join the complaint, but acting through the association keeps the case focused on the common issues.
This example is illustrative only. The outcome in a real case depends on its documents, facts and the forum’s view.
Need help?
If this affects your flat or project, the office of Adv. Mridul Jindal handles RERA complaints and pending registry cases. You can contact us for a consultation in person at Indirapuram or online.
Related sections
Frequently asked questions
Who must obtain the occupancy certificate?
The promoter, under Section 11(4)(b), and make it available to the allottees or their association.
Can the builder cancel my booking?
Only in terms of the agreement for sale (Section 11(5)); one-sided or unfair cancellations can be challenged before RERA.
Who pays property tax and land dues before possession?
The promoter, until physical possession is handed over to the allottees (Section 11(4)(g)).
What if the advertisement promised things not delivered?
Section 12 makes the promoter liable to compensate or refund for false statements in an advertisement or prospectus.
Must a builder keep buyers’ money in a separate account?
Yes. Section 4(2)(l)(D) requires 70 per cent of amounts realised to be kept in a separate account for construction and land cost of that project.
When must the builder help form the residents’ association?
Within three months of a majority of allottees having booked, under Section 11(4)(e), unless local laws provide otherwise.
Prepared by the office of Adv. Mridul Jindal. Last updated 29 November 2026. This page is general legal information, not legal advice for your specific case. Law and procedure change; please consult an advocate before acting.