In short: Under Section 18 of the Real Estate (Regulation and Development) Act, 2016, if the promoter fails to complete or give possession as per the agreement for sale (or because of discontinuance of business), the allottee has a choice: withdraw and get a refund of all amounts paid with interest and compensation, or stay in the project and get interest for every month of delay until possession. Section 18(2) gives compensation for loss due to defective title, and Section 18(3) for other breaches.

हिंदी में: धारा 18 रेरा: कब्जे में देरी पर खरीदार ब्याज सहित पूरी राशि वापस ले सकता है, या परियोजना में बने रहकर देरी के हर महीने का ब्याज पा सकता है।

Section 18 RERA at a glance

ProvisionWhat it says (summary)
18(1)(a)-(b)Failure to complete or give possession by the agreed date, or discontinuance of business.
If the allottee withdrawsRefund of the entire amount paid, with interest at the prescribed rate, plus compensation.
If the allottee staysInterest for every month of delay until possession is handed over.
18(2)Compensation for loss due to defective title to the land.
18(3)Compensation for failure to discharge other obligations under the Act, rules or agreement.

The table summarises the provisions in plain English. For the exact words and the State rules (UP RERA, Delhi RERA), see the Act on India Code.

An unconditional right

In M/s Newtech Promoters and Developers Pvt. Ltd. v. State of U.P. (2021) 18 SCC 1, the Supreme Court held that the allottee’s right to a refund with interest under Section 18(1) is unqualified and does not depend on unforeseen events or stay orders. It also held that the Authority can order refund and interest, while compensation is decided by the adjudicating officer.

Interest rate

The rate is prescribed by the State’s RERA rules and is generally linked to the State Bank of India’s marginal cost of lending rate (MCLR) plus a margin. The same rate applies to the allottee’s delayed payments, so the rules are balanced. The exact current rate in UP or Delhi is worth checking.

Recovering the money

If the builder does not pay, the Authority issues a recovery certificate under Section 40, and the amount is recovered as arrears of land revenue through the district administration. See builder delay and refund.

The Newtech principle

In Newtech Promoters and Developers Pvt. Ltd. v. State of Uttar Pradesh, 2021 INSC 762, the Supreme Court described the allottee’s right to refund under Section 18(1)(a) and Section 19(4) as an unqualified right if the promoter fails to give possession within the time stipulated in the agreement, regardless of unforeseen events or stay orders, because the promoter alone is responsible for completing the project. The obligation to pay interest is a statutory consequence of the delay. Where the allottee does not wish to withdraw, the promoter must pay interest for every month of delay until handing over possession.

Refund or possession: making the choice

  • Refund suits buyers who have lost confidence in the project or need the money; it comes with interest from the date of each payment.
  • Possession with delay interest suits buyers who still want the flat, especially if prices have risen since booking.
  • If the project is close to completion with an occupancy certificate, Authorities sometimes encourage possession; if it is stalled, refund is usually preferred.
  • A buyer who chose possession can later seek refund only in limited circumstances, so decide carefully.

Step by step: claiming under Section 18

  1. Check the possession date in the registered agreement and any extension registered on the RERA portal.
  2. Send a notice demanding possession or refund with interest.
  3. File a complaint before the State RERA Authority seeking refund or delay interest.
  4. File a separate compensation application before the adjudicating officer if needed.
  5. Seek a recovery certificate under Section 40 if the order is not complied with.

Common mistakes

  • Accepting a revised possession date in writing without reserving delay interest.
  • Taking possession and signing a no-claim declaration without objection.
  • Waiting for the project to be stalled for years before acting.

An example

Sunita booked a flat with promised possession in December 2021. By 2025 the tower is incomplete and the builder offers a new date in 2027. Sunita decides she no longer wants to wait. She files a complaint before UP RERA under Section 18 seeking refund of the full amount with interest from each payment date, relying on Newtech. The builder argues that a pandemic and a construction ban caused the delay. The Authority’s task is to apply the Act and the Supreme Court’s reading of it; Sunita also files a compensation application before the adjudicating officer for the rent she paid while waiting.

This example is illustrative only. The outcome in a real case depends on its documents, facts and the forum’s view.

Need help?

If this affects your flat or project, the office of Adv. Mridul Jindal handles builder delay and refund cases and RERA complaints in Ghaziabad. You can contact us for a consultation in person at Indirapuram or online.

Related sections

Frequently asked questions

Can I get a full refund if my flat is delayed?

Yes. Under Section 18, you can withdraw and get the entire amount paid back with interest, plus compensation.

What if I want the flat, not a refund?

You can stay in the project and claim interest for every month of delay until possession.

Can the builder use Covid or court orders as an excuse?

The Supreme Court held in Newtech (2021) that the right to a refund is unconditional and not subject to such events.

Who decides compensation?

The adjudicating officer under Section 71; the Authority decides refund and interest.

Is the right to a refund under RERA absolute?

The Supreme Court in Newtech (2021) called it unqualified where the promoter fails to give possession within the agreed time, irrespective of unforeseen events.

Should I sign a no-dues or no-claim letter at possession?

Read it carefully. If you have a delay interest claim, record your objection or reservation in writing.

Prepared by the office of Adv. Mridul Jindal. Last updated 29 November 2026. This page is general legal information, not legal advice for your specific case. Law and procedure change; please consult an advocate before acting.

Stay Legally Informed

Free legal updates in your inbox. No spam.

Chat on WhatsApp