Sections 73 to 75 Indian Contract Act: Damages, Penalty and Liquidated Damages

Sections 73 to 75 Contract Act: Damages for Breach: Remoteness, Liquidated Damages, Penalty and Earnest Money
Share

Home › Law Library › Indian Contract Act › Sections 73 to 75

In short: Under Section 73 of the Indian Contract Act, 1872, the party who suffers from a breach is entitled to compensation for loss that naturally arose from it or that the parties knew was likely, but not for remote or indirect loss. Section 74 caps recovery at the amount named in the contract, whether called liquidated damages or a penalty, and allows only reasonable compensation. Section 75 lets a party who rightly rescinds claim compensation too.

हिंदी में: धारा 73: अनुबंध टूटने पर उस नुकसान का मुआवज़ा मिलता है जो स्वाभाविक रूप से हुआ या जिसकी दोनों पक्षों को संभावना पता थी; दूर के या अप्रत्यक्ष नुकसान का नहीं। धारा 74: अनुबंध में तय राशि अधिकतम सीमा है, और केवल उचित मुआवज़ा मिलता है। धारा 75: अनुबंध उचित रूप से रद्द करने वाला पक्ष भी मुआवज़ा मांग सकता है।

Key facts

ProvisionWhat it says (summary)
Section 73, para 1Compensation for loss or damage that naturally arose in the usual course from the breach, or that the parties knew when contracting was likely to result from it.
Section 73, para 2No compensation for remote and indirect loss or damage.
Section 73, ExplanationIn assessing loss, the means available to remedy the inconvenience caused by non-performance are taken into account (duty to mitigate).
Section 73, para 3The same rules apply to failure to discharge an obligation resembling a contract (quasi-contract).
Section 74Where a sum is named as payable on breach, or a penalty is stipulated, the injured party gets reasonable compensation not exceeding the amount named, whether or not actual loss is proved.
Section 74, ExceptionBail bonds, recognisances and similar instruments given to the Government are enforceable for the whole sum.
Section 75A person who rightfully rescinds a contract is entitled to compensation for damage sustained through non-fulfilment.

The table summarises the provisions in plain English. For the exact words, see the Indian Contract Act, 1872 on India Code.

Remoteness and mitigation

Section 73 reflects the rule in Hadley v. Baxendale: you recover losses that flow naturally from the breach, and special losses only if the other side knew of the special circumstances when contracting. Loss of profit on a specific resale, for example, needs proof that the seller knew of it.

The Explanation requires the injured party to take reasonable steps to reduce the loss. A buyer who does not get goods should buy elsewhere and claim the difference in price, not wait while the market rises.

Liquidated damages and penalties under Section 74

Indian law does not distinguish sharply between liquidated damages and penalties. The amount named is the upper limit, and the court awards reasonable compensation within it.

  • In Fateh Chand v. Balkishan Das (1963), the Supreme Court held that the court awards reasonable compensation not exceeding the stipulated sum, and a clause allowing forfeiture of a large part payment was treated as a penalty.
  • In ONGC v. Saw Pipes (2003), the Court held that where the stipulated sum is a genuine pre-estimate of loss, it can be awarded without proof of actual loss, especially where loss is difficult to prove.
  • In Kailash Nath Associates v. DDA (2015), the Court clarified that damage or loss is still essential: where no loss is caused, nothing can be recovered, and where loss can be proved, it must be proved.

Earnest money and forfeiture

Earnest money given as a guarantee of performance can generally be forfeited if the payer defaults, when the contract so provides. But where the amount forfeited is in the nature of a penalty, or is not true earnest money but a part payment of price, courts apply Section 74 and allow only reasonable compensation. Large forfeitures in property deals are frequently challenged on this basis.

Interest and costs

Compensation can include interest where the contract provides for it or where the law allows; courts also award pendente lite and future interest under Section 34 of the CPC. Commercial suits follow cost rules under the Commercial Courts Act.

Typical Delhi NCR situations

  • A Ghaziabad buyer backs out of a plot purchase; the agreement allows the seller to forfeit 30 per cent of the price as “earnest”. A court may treat this as a penalty and allow only reasonable compensation.
  • A Noida manufacturer receives defective components and loses a specific export order. Loss of that order is recoverable only if the supplier knew of it when contracting.
  • A Delhi contractor finishes late; the contract provides 0.5 per cent per week as liquidated damages. The employer can claim within that cap, subject to showing loss as per Kailash Nath.

Step by step: preparing a claim for damages

  1. Identify the breach and the date it occurred.
  2. List each loss and link it to the breach; separate ordinary losses from special losses.
  3. Collect proof of the other side’s knowledge of special circumstances.
  4. Show what you did to mitigate: alternative purchase, resale, cover arrangements.
  5. Check any liquidated damages clause and treat the sum named as the cap.
  6. Send a legal notice and file within limitation, normally three years.

Common mistakes

  • Claiming the full liquidated damages amount without any evidence of loss.
  • Failing to mitigate and then claiming the entire market difference.
  • Forfeiting large “earnest money” sums that are really part payments.
  • Claiming remote losses like loss of reputation without a clear basis.

Need help?

If this affects your matter, the office of Adv. Mridul Jindal advises on contract drafting and review, commercial suits, arbitration and civil recovery and property disputes in Delhi, Ghaziabad and Noida. For recovery claims, see also money recovery. You can contact us for a consultation in person at Indirapuram or online by WhatsApp video, Google Meet or phone.

Related guides

Frequently asked questions

What damages can I claim for breach of contract in India?

Losses that naturally arise from the breach, or that both sides knew were likely when contracting. Remote and indirect losses are excluded.

Is a liquidated damages clause enforceable?

The amount named is the maximum. The court awards reasonable compensation within it, and loss must generally be shown, as held in Kailash Nath Associates v. DDA (2015).

Can a seller forfeit earnest money?

True earnest money can generally be forfeited on the buyer’s default if the contract says so, but excessive forfeiture is treated as a penalty under Section 74.

Do I have to reduce my losses after a breach?

Yes. The Explanation to Section 73 takes into account the means available to remedy the loss.

Can I claim compensation if I cancel the contract?

Yes. Section 75 allows a party who rightfully rescinds to claim compensation for damage sustained.

Prepared by the office of Adv. Mridul Jindal. Last updated 29 November 2026. Case references checked against published reports. This page is general legal information, not legal advice for your specific case. Law and procedure change; please consult an advocate before acting.