Section 3 RERA: Mandatory Registration of Real Estate Projects, Exemptions, and Ongoing Projects

Section 3 RERA: Mandatory Registration of Real Estate Projects, Exemptions, and Ongoing Projects
Share

Home › Law Library › RERA › Section 3

In short: Under Section 3 of the Real Estate (Regulation and Development) Act, 2016, a promoter cannot advertise, market, book, sell or offer any plot, apartment or building in a real estate project without registering the project with the State RERA Authority. Ongoing projects without a completion certificate on the date the section came into force also had to be registered. Projects on land not exceeding 500 square metres, or with not more than eight apartments, are exempt, as are projects with a completion certificate issued before the Act and certain renovation works.

हिंदी में: धारा 3 रेरा: बिल्डर बिना परियोजना पंजीकरण के फ्लैट या प्लॉट का विज्ञापन या बिक्री नहीं कर सकता; 500 वर्ग मीटर तक या आठ अपार्टमेंट तक की परियोजनाएँ छूट प्राप्त।

Section 3 RERA at a glance

ProvisionWhat it says (summary)
3(1)No advertising, marketing, booking, selling or offering of plots or apartments without registration; ongoing projects without a completion certificate also must register.
3(2)(a)Exemption: land not exceeding 500 square metres or not more than eight apartments (States can lower these limits).
3(2)(b)Exemption: projects with a completion certificate issued before the Act came into force.
3(2)(c)Exemption: renovation or repair not involving marketing or allotment of new units.
Sections 4-7Application, grant, extension and revocation of registration.
Section 59Penalty for non-registration: up to 10% of the estimated project cost, and imprisonment for continued violation.

The table summarises the provisions in plain English. For the exact words and the State rules (UP RERA, Delhi RERA), see the Act on India Code.

Why registration matters to a buyer

A registered project has its sanctioned plans, approvals, completion timeline and the promoter’s details on the RERA website. Under Section 4, the promoter must keep 70% of the amounts collected from buyers in a separate account to be used only for that project’s land and construction cost. Before booking, check the project’s registration number on the UP RERA or Delhi RERA website.

Ongoing projects

In M/s Newtech Promoters and Developers Pvt. Ltd. v. State of U.P. (2021) 18 SCC 1, the Supreme Court held that the Act applies to ongoing projects that did not have a completion certificate when it came into force, so buyers of such projects can use RERA remedies such as Section 18.

Real estate agents

Under Section 9, real estate agents must also register with the Authority before facilitating sales in registered projects.

Which projects must register

Section 3(1) prohibits a promoter from advertising, marketing, booking, selling or offering for sale any plot, apartment or building in a real estate project in a planning area without registering the project with the State RERA. Ongoing projects that had not received a completion certificate when the Act commenced had to register within three months. Section 3(2) exempts projects where the land proposed to be developed does not exceed 500 square metres or the number of apartments does not exceed eight, inclusive of all phases, projects that had received a completion certificate before commencement, and renovation or repair that does not involve marketing or new allotment. States may lower the area threshold. Where a project is developed in phases, each phase is treated as a stand-alone project for registration.

Consequences of not registering

Under Section 59, a promoter who fails to register is liable to a penalty of up to 10 per cent of the estimated cost of the project, and continued violation can lead to imprisonment of up to three years, or a further fine of up to another 10 per cent, or both. The buyer of an unregistered project is not left without remedy: the agreement and payments remain, and remedies under RERA against the promoter, consumer law and civil law may be available depending on the facts. Selling without registration is also a strong ground to seek refund.

Step by step: checking a project before booking

  1. Search the State RERA website (UP RERA or Delhi RERA) by project name or registration number.
  2. Read the declared completion date, the sanctioned plans and the quarterly updates.
  3. Check the promoter’s other projects for delays and complaints.
  4. Confirm the agent is also registered under Section 9.
  5. Keep a screenshot of the registration page as it stood on the booking date.

Common mistakes

  • Relying on the builder’s word that registration is applied for.
  • Not checking the declared completion date, which may be later than the one in the brochure.
  • Dealing with an unregistered agent.

An example

Ravi books a two-bedroom flat in a new tower in Greater Noida West after seeing a newspaper advertisement. Before paying, he searches the UP RERA website and finds that the tower is registered as a separate phase with a declared completion date two years later than the date printed in the brochure. He raises this with the builder, who agrees to record the earlier date in the agreement for sale. Ravi also notices that the broker who showed him the flat is not registered under Section 9, so he deals with the builder’s sales office directly. When construction later slows, the registration page and quarterly updates he saved become his main evidence of what was promised and when.

This example is illustrative only. The outcome in a real case depends on its documents, facts and the forum’s view.

Need help?

If this affects your flat or project, the office of Adv. Mridul Jindal handles RERA complaints in Noida and RERA complaints in Ghaziabad. You can contact us for a consultation in person at Indirapuram or online.

Related sections

Frequently asked questions

How do I check if a project is RERA registered?

Search the project or promoter name on the State RERA website (UP RERA for Ghaziabad and Noida, Delhi RERA for Delhi) and check the registration number and validity.

Are small projects exempt from RERA?

Yes. Projects on land up to 500 square metres or with up to eight apartments are exempt under Section 3(2)(a), unless the State has set lower limits.

Does RERA apply to projects started before 2017?

Yes, to ongoing projects that did not have a completion certificate when the Act came into force, as held in Newtech Promoters (2021).

What if the builder sold flats without registration?

It is a violation punishable under Section 59, and buyers can still complain to the Authority.

What is the penalty for not registering a project under RERA?

Up to 10 per cent of the estimated project cost under Section 59, with imprisonment of up to three years or a further fine for continued violation.

Is each phase of a project registered separately?

Yes. Where a project is developed in phases, each phase is treated as a stand-alone real estate project for registration.

Prepared by the office of Adv. Mridul Jindal. Last updated 29 November 2026. This page is general legal information, not legal advice for your specific case. Law and procedure change; please consult an advocate before acting.