Home › Law Library › Specific Relief Act › Section 20
In short: Section 20 of the Specific Relief Act, 1963, inserted in 2018, allows a party who suffers a breach to obtain substituted performance: getting the work done through a third party or its own agency and recovering the costs from the defaulting party. A written notice of at least 30 days must first be given. A party who opts for substituted performance cannot then claim specific performance. Section 20A bars injunctions that would impede infrastructure projects, Section 20B provides for Special Courts, and Section 20C requires such suits to be decided within 12 months of service of summons, extendable by 6 months.
हिंदी में: धारा 20 विनिर्दिष्ट अनुतोष अधिनियम (2018): अनुबंध भंग होने पर तीसरे पक्ष से कार्य करवाकर लागत चूककर्ता से वसूलना; 30 दिन का नोटिस आवश्यक।
Section 20 at a glance
| Provision | What it says (summary) |
|---|---|
| 20(1) | On breach, the aggrieved party may obtain substituted performance through a third party or its own agency and recover the costs. |
| 20(2) | Written notice of not less than 30 days must be given to the party in breach. |
| 20(3) | Having obtained substituted performance, the party cannot claim specific performance, but can claim compensation. |
| 20(4) | The right to compensation is not affected. |
| Section 20A | No injunction where it would impede or delay an infrastructure project. |
| Section 20B | Special Courts for infrastructure project suits. |
| Section 20C | Suits to be decided within 12 months of service of summons, extendable by 6 months. |
The table summarises the provisions in plain English, as amended by the Specific Relief (Amendment) Act, 2018. For the exact words, see the Act on India Code.
How it works in practice
Suppose a contractor abandons interior or construction work midway. Instead of suing for specific performance, the owner may give 30 days’ written notice, get the work completed by another contractor, and recover the extra cost from the first contractor. The notice and proper records of the costs are essential.
Effect on other remedies
Once substituted performance is obtained, Section 16(a) and Section 14(a) bar specific performance. Damages remain available for other losses.
Speedy disposal
Section 20C applies to all suits under the Act, not only infrastructure suits, and requires disposal within 12 months from service of summons, extendable by 6 months for reasons recorded. In practice, courts treat this as a target rather than a strict bar.
The notice and timeline
Under Section 20, where a contract is broken due to non-performance of promise by a party, the affected party can get the contract performed through a third party or its own agency, and recover the expenses and costs from the defaulting party. It must first give the defaulter a notice in writing of not less than 30 days, asking for performance within the time specified. If the defaulter does not perform, the affected party can proceed with substituted performance. Once it has done so, it cannot claim specific performance against the defaulter, though it can still claim compensation.
Infrastructure projects and special courts
The 2018 amendment added Sections 20A, 20B and 20C. Section 20A bars a court from granting an injunction in a suit involving a contract relating to an infrastructure project specified in the Schedule, where the injunction would cause impediment or delay. Section 20B requires States, in consultation with High Courts, to designate civil courts as Special Courts for suits relating to infrastructure contracts. Section 20C asks courts to dispose of suits under the Act within 12 months of service of summons, extendable by six months for reasons recorded.
Step by step: using substituted performance
- Record the default in writing and keep evidence of the incomplete work.
- Send a written notice giving at least 30 days to perform.
- If there is no performance, engage another contractor at a reasonable cost.
- Keep invoices and measurements to prove the cost of substituted performance.
- Claim the cost and any compensation from the defaulter.
An example
A builder of a small office in Noida stops work halfway. The owner sends a 30-day notice under Section 20 asking him to resume. When nothing happens, the owner engages another contractor, documents the remaining work and the cost, and then sues the first builder for the extra expense. Having chosen substituted performance, the owner cannot also ask the court to force the first builder to finish.
This example is illustrative only. The outcome in a real case depends on its documents, facts and the court’s view.
Need help?
If this provision affects your case, the office of Adv. Mridul Jindal handles contract disputes and drafting and commercial suits. You can contact us for a consultation in person at Indirapuram or online.
Related sections
- Section 10 Specific Relief Act
- Section 14 Specific Relief Act
- Section 41 Specific Relief Act
- All sections of the Specific Relief Act
- Code of Civil Procedure in the Law Library
Frequently asked questions
Do I need a court order to get substituted performance?
No. Section 20 is a self-help remedy, but you must give at least 30 days’ written notice and keep proof of costs; recovery of costs may need a suit.
Can I still ask for specific performance after substituted performance?
No. Section 20(3) and Section 16(a) bar it.
Can a court stop an infrastructure project by injunction?
Not where the injunction would impede or delay the project, under Sections 20A and 41(ha).
Is there a time limit for deciding specific relief suits?
Section 20C sets 12 months from service of summons, extendable by 6 months.
How much notice must be given before substituted performance?
At least 30 days in writing, asking the defaulter to perform within the specified time.
Can I seek specific performance after getting the work done by someone else?
No. Once substituted performance is obtained, specific performance against the defaulter is not available, though compensation is.